Construction progress for July
Block 2
Work is ongoing on the arrangement of the central facade (on the side of Antonovycha Street) with Reynaers translucent aluminum enclosing structures. The installation of Reynaers translucent aluminum fencing structures on the facade from the courtyard is in progress. Schindler elevator equipment is 100% installed.
Block 3
Monolithic work on the extension (kindergarten) — lower floors — is ongoing. Work on the installation of walls and partitions is also ongoing. Installation of the ventilation system is in progress.
General household works
Preparatory work on the installation of external water supply and sewerage engineering networks is underway.
From 30 to 43 construction workers work on the site every day.