Construction progress for April

Block 1

Work continues on the installation of translucent aluminum enclosing structures by Reynaers. Readiness is more than 40%. The installation of elevator equipment is nearing completion. The construction of the K2 in-house rainwater drainage system is almost 70% complete.

Block 2

The installation of Reynaers translucent aluminum enclosing structures on the façade from the courtyard continues. Readiness is more than 80%.

Block 3

Roofing work continues. Readiness 95%. The work on installing the K2 in-house rainwater drainage system is more than 90% complete. Work on finishing the technical premises continues.

Block 4

The work on installing the K2 in-house rainwater drainage system is 95% complete.

Parking

Monolithic work on the construction of the frame is almost completed.

From 22 to 29 builders work on site every day